January 2023
On December 8, 2022, the Community Preservation Committee found the first-floor renovations of the Masonic Hall to be eligible for CPC funding. The scope of work is to upgrade the utilities, add floor joists, clear out the old Kitchen appliances, remove the stage, and add bathrooms. While the scope of work is limited to the first floor, we will also be pulling in the North Side of the building to ensure the entire structure is safe. On Monday, January 9, 2022, the Select board signed the lease agreement with the Food Pantry during their scheduled meeting.